Line 3 capper jam — double cap

Production · June 21, 2026 · Lead: Jamie R.

Demo report

Problem

After a capper tool changeover, Line 3 ran ~7 minutes with the cap chute guard un fitted, producing double caps on ~40 units before the checkweigher caught the defect.

Fishbone

After a capper tool changeover, Line 3 ran ~7 minutes with the cap chute guard un fitted, producing double caps on ~40 units before the checkweigher caught the defect.After a capper tool c…PEOPLEMETHODChangeover checklist has no mandatory guard-fit verification stepChangeover checklist has no…Line 3 changeover SOP lacks guard-fit sign-off before run approvalLine 3 changeover SOP lacks…MEASUREMENTDouble caps detected at checkweigher (~40 units on Line 3)Double caps detected at che…EQUIPMENTCapper chute guard not fitted after tool changeoverCapper chute guard not fitt…Cap chute alignment drift after tool change (Maintenance scope) → MaintenanceCap chute alignment drift a… →Maintena…MATERIALENVIRONMENT

● verified · assumed · ◆ root cause · → handed to another team

Causal chain

  • Symptom

    Double caps detected at checkweigher (~40 units on Line 3)

  • Contributing cause· verified

    Capper chute guard not fitted after tool changeover

    Maintenance log and shift handover confirm guard removed at 14:08, not refitted before run.

  • Contributing cause

    Changeover checklist has no mandatory guard-fit verification step

  • Root cause· verified

    Line 3 changeover SOP lacks guard-fit sign-off before run approval

    SOP v4.2 reviewed — no guard verification gate before line release.

  • Contributing cause

    Cap chute alignment drift after tool change (Maintenance scope)

Verified root cause

Line 3 changeover SOP lacks guard-fit sign-off before run approval

SOP v4.2 reviewed — no guard verification gate before line release.

Owned actions

  • Add guard-fit check to Line 3 changeover checklist with signed verification before run

    Jamie R. · review by 2026-07-06 · Zero double-cap events for 30 days post-implementation

  • Daily pre-run guard inspection at capper station 3 (visual + tactile)

    Jamie R. · review by 2026-06-29 · 100% completion on shift-start checklist for 2 weeks

Handoffs

  • Training: Operators not trained on guard importance at changeover

    Need refresher for all Line 3 operators — guard purpose and fit verification.